Construction Projects- June 12, 2025

  1. Paving projects in 2025 –  (Please note, it might not be the entire segment of road)

Anderson Road, Brummetts Creek Road, Burma Road, Cowden Road, Hartstrait Road, Lampkins Ridge Road, Maple Grove West, Old SR 37 North, Popcorn Road, Springville Road, Shilo Road, Strain Ridge Road, Vernal Pike, Pine Grove Road, Deer Lick Road, Holly Lane, Darrell Drive, Darrell Court, Lori Ann Lane, Williams Way, Inverness Woods Road, Inverness Crest, Cranbrook Road, Spring Branch Road, Park Square Drive, Union Valley Road, Stipp Road, John Young Road, Lower Birdie Galyan Road, Coyle Road, Merritt Drive, Miller Road, Eller Lane, Eller Road, Kings Road, Rockeast Road, Elwren Road, Flatwoods Road and Fox Lane.

  1. Community Crossings Grant Projects - Monroe County was awarded the 1.5 million for paving projects through INDOT in 2025.  CCMG is changing as we move forward and there will be only one call per year and much more competitive across the state since the funding has lowered.  
  2. Stipp Road/Moores Creek Road Project- These projects are listed in the Long Range Stormwater Plan, Items #4 and #16. Moores Creek end was completed in 2024.  Stipp Road was awarded to E&B Paving .  The utilities have been relocated and we anticipate a July/August starting date and the project completed in 2025.  After the Stormwater project is completed, E&B will pave the entire portion of Stipp Road to Moffett Lane.
  3. Vernal Pike Trail - Staff has been working with Redevelopment Commission for the funding of this project. 
  4. Baby Creek Stormwater Project -  This project is listed in the Long Range Stormwater Plan, Item #3.  It is the goal to replace one culvert in 2025.
  5.  Vernal Pike Connector Road - The project was awarded to Force Construction on February 16, 2024 and is under construction. The road is scheduled to open in August 2025 and will also add a traffic signal at Vernal Pike and Sunrise Greetings Court. 
  6. Rockport Road, Bridge #308 - This bridge replacement project is under design. Right-of-way acquisition has began. Letting date is February 11, 2026.
  7. Baby Creek Road, Bridge #629 - Awarded funding for construction in 2027.  Project is currently under the design phase and right-of-way acquisition has started.  Letting date is October 7, 2026.
  8. Dillman Road, Bridge #83 - Monroe County was awarded $2.3 million for the bridge replacement.  Construction is in FY2028.  The existing steel truss bridge will be used on a future trail.  Letting date is December 8, 2027.
  9. That Road, Bridge #79 -  Design is complete and right-of-way acquisition has started.  The project has received federal funding for construction in FY2029.
  10. Rhorer Road, Bridge #75 -  Bids were opened in May 2025.  The lowest bidder (six bids received) was CLR.  The Board of Commissioners awarded the project to CLR on June 12, 2025.  Construction will most likely occur in 2026 due to other projects that are under construction and would affect the detour routes.
  11. Mt. Tabor Road, Bridge #13- The project is under design with right-of-way acquisition to begin fall of 2025.
  12. Pedestrian Improvement Project - The project is funded by HSIP funds within the MPO.  There are seven locations at trail crossings that will have flashing beacons installed.  The project has begun and will be completed by the end of 2025.
  13. Old SR 37 South and Dillman Road Intersection Improvement - Funds have been allocated through the MPO to begin design in 2026 with a 2028 construction season.  The project is currently planned to install a round-about at this intersection to improve sight distance or overall safety improvement.  
  14. Fullerton Pike, Phase III- The project has been awarded to Milestone Contractors.   Construction will began on April 9, 2024 and will begin on the west end at Rockport Road.  Opening of the bridge and roadway is expected before August 4, 2025.  The project consists of a 525' bridge and roadway connection with the installation of a roundabout at Bachelor Drive and Gordon Pike. 
  15. Business 37 North, Bridge #913 Replacement- Monroe County was awarded the project in February 2025.  Construction is currently scheduled for FY 2029 or 2030.  Monroe County has chosen USI Consultants for the design of the project.  The firm was chosen following all federal aid guidelines with INDOT. 
  16. Fairfax Road, safety improvements- The project is utilizing HSIP funds through INDOT’s safety program.  We will have high-friction surface treatment installed on certain areas that have experienced a high-run off the road crashes.  The project is to be let in the Fall of 2025 or Spring of 2026.
  17. Eagleson Bridge #922 – The bridge has been designed and right-of-way is completed.  The letting for this bridge replacement is January 14, 2026.

 

Contact Us

Lisa Ridge,
Highway Director
5900 W Foster Curry Dr
Bloomington, IN 47403
Get Directions
  • Phone: (812) 803-6810
  • Phone: (812) 349-2555
  • Fax: (812) 825-5358
  • Staff Directory
  • M - F 7:00 a.m. - 3:30 p.m.

In this Department

Topics of Interest

More Information

Find content and services related to this page.