County Road Construction Projects Minimize

Sample Road - Right-of-way acquisition has begun in January 2018 for Phase I (Old SR 37 North to I69).  Phase II has been submitted to INDOT in the NOFA FY22 Call for Projects, Project to be presented to INDOT panel on January 11, 2018, awards announced in February 2018

Cedar Ford Covered Bridge - CLR was awarded the project.  Construction is in 2018

Fullerton Pike, Phase I - Under Construction, to be completed in 2018.

Fullerton Pike Phase II, 10 of 11 Parcels acquired, last parcel has been accepted and finishing final paperwork.  Working with the Historical Society on the possible relocation of the Carter house vs demolition

Kinser Pike Bridge #46 - Project is complete. Road opened 11/22/2017.  Ongoing meetings with INDOT, Monroe County, Contractor and Beam concerning claims and invoices

Hunters Creek Road - E&B Paving was awarded the project.  They will begin construction around April 1, 2018 for Phase I.  Pre-construction meeting was held January 5, 2018. Phase II has been submitted to INDOT in the NOFA FY22 Call for Projects, Project to be presented to INDOT panel on January 11, 2018, awards announced in February 2018

Bicentennial Pathway Project - Contracts have been signed for PE and the Consultant has been given the NTP. Letting date 9/2020

Curry Pike/Smith Pike/Woodyard Road Intersection Improvement Project - Received contract from WSP and sent to Dave Schilling for review.  Meeting with WSP on Thursday, January 11, 2018 to discuss the scope of service for the project. 

County Wide Bridge Inspections FY 2018-2022 - Contract signed with Beam.  Contract with INDOT for Project Coordination is on the agenda for the next work session for the Commissioners approval.  Phase I begins in March 2018.

Karst Farm Park Trail, Phase 2B - Requested 4 quotes and received 2, Milestone and CLR.  CLR was the lowest most responsive quote.  Hope to get these repaired this spring.

Community Crossings Grant Projects -These are the remaining roads that will be completed this year:

   1) Old SR 37 South, from Rogers Road to Monroe Dam Road exit
   2) Kirby Road
   3) Airport Road

Industrial Park Drive - Submitted the project in the NOFA FY22 Call for Projects with INDOT.  Presenting the project to the panel on January 11, 2018.  Awarded projects will be announced in February 2018.  Joyce Poling with Ivy Tech and Dan Peterson with Cook, Inc. will be presenting the project with myself on the 11th.

Mt. Tabor Road, Bridge #13 Stormwater Project - Submitted the project in the NOFA FY22 Call for Projects with INDOT.  Presenting the project to the panel on January 11, 2018.  Awarded projects will be announced in February 2018.

Bottom Road Bridge, #21, Cumulative Bridge and Stormwater Project - Preliminary Engineering is being completed at this time.

Stipp Road/Moores Creek Road Stormwater Project - Preliminary Engineering is being conducted, working on Topo and Wetland reports

Hartstrait Road/Daniels Way Road Connection - Working with the remaining businesses for ROW acquisition, all other ROW has been acquired. Anticipate late 2018 construction.

Vernal Pike Trail - Working with VS Engineering and Smith/Brehob on some changes that the railroad has requested.  Hoping for a 2018 construction.

Country Club Drive, Bridge #73 - This is the last Community Crossing Grant project from 2016.  CLR was awarded the project, anticipate construction to begin March 2018

2018 Cumulative Bridge Program - Will begin the process of compiling the projects for the upcoming year

 

Pavement Striping Program

The striping program will begin in May of 2010. The condition of the pavement markings on various roads throughout the County will be assessed for the need to improve the markings.

Annual Bridge Projects

2007 Cumulative Bridge Program
2008 Cumulative Bridge Program
2009 Cumulative Bridge Program
2010 Cumulative Bridge Program
2011 Cumulative Bridge Program                            
2011 Cumulative Bridge Program
2012 Cumulative Bridge Program
2013 Cumulative Bridge Program
2014 Cumulative Bridge Program
2015 Cumulative Bridge Program
2016 Cumulative Bridge Program


You will need to download Adobe Acrobat Reader to read or print these Reports

Trail Projects

Karst Farm Greenway Environmental